Floodway Feud: East Branch Dispute Sharpens as DEC Calls For Corrective Action

Posted

HANCOCK - A long-simmering dispute over alleged illegal dumping in an East Branch floodplain by Johnston & Rhodes, a bluestone company, reached a boiling point as Hancock Supervisor Jerry Vernold and the New York State Department of Environmental Conservation (DEC) offered starkly different interpretations of the same regulatory letter.

In a press release issued April 16, Vernold struck a triumphant tone, claiming the DEC had “confirmed the longstanding, authorized nature” of operations at the Johnston & Rhodes Bluestone property. However, an April 10 letter from the DEC’s Dave Sherman to Vernold, the town board and town attorney, tells a more complicated story - one of shifting maps, unauthorized fill, and a looming threat to the town’s federal flood insurance standing.

The Press Release vs. The Reality

Vernold’s announcement focused heavily on the historical legitimacy of the site, quoting the DEC’s acknowledgment that material storage has occurred there since the 1970s.

“DEC’s letter confirms what we have maintained throughout — that Johnston & Rhodes has a longstanding, permitted operation at this site,” Vernold stated.

But the DEC’s letter to Vernold clarifies that “longstanding” does not mean “exempt.” While a 1978 permit allowed for some activity, the DEC noted that federal requirements have evolved significantly as flood maps were updated in 1990 and 2012.

“Due to the historical FIRM [Flood Insurance Rate Map] changes and the floodway, the requirements for utilizing the area have changed and have become more restrictive,” Sherman wrote in the April 10 letter. He pointed out that while the site once held “random piles of material,” recent activity has filled in the entire area - a change that exceeds the historical baseline.

A “Pathway” or a Violation?

Vernold’s press release highlights a “clear compliance pathway,” suggesting a cooperative resolution. The DEC, however, framed these “options” as necessary corrective actions for alleged unpermitted development:

• Removal: The town may require the owners to remove the fill and restore the property.

• Engineering Analysis: If the fill remains, the owners must hire an engineer for a “no-rise” analysis to prove flood elevations are not affected.

• Map Revision: If a rise in floodwater is detected, the owner must mitigate it or undergo a formal FEMA map revision.

The DEC was blunt about the town’s responsibility: “Enforcement of the floodway regulations... is the responsibility of the town as the participating member of the National Flood Insurance Program (NFIP).” Sherman warned that failure to regulate these areas could jeopardize residents’ access to federally backed flood insurance and disaster assistance.

Neither interpretation could be independently verified as definitive pending DEC enforcement action.

Background: A “Muck” of Legal Silence

The dispute first surfaced in July 2025 when East Branch resident Bradley Elmore began complaining about “stone muck” - a cutting byproduct - being dumped over embankments. Elmore alleged the runoff contaminated his family’s drinking water well, “literally turning it to mud.”

Previous reporting by The Reporter revealed a pattern of “deferred oversight” by town officials:

• The “Phantom” Permit: According to documents obtained through FOIL, Hancock town attorney Leonard Sienko previously cited a 1978 DEC permit as a defense for the dumping. Residents allege that the permit was non-transferable and specifically for bridge construction, not mass filling.

• Political Pressure: A recorded call reviewed by The Reporter surfaced in which Hancock Code Enforcement Officer Josh Morgan told Elmore he was directed by the town attorney “not to do anything” regarding the alleged violations.

• The Unpermitted Garage: A garage was constructed atop the “unstable” fill at a neighboring site (10 Bridge Street) without a building permit. A stop-work order was only issued after construction was complete and media inquiries began.

The DEC Weighs In

Despite Vernold’s earlier public claims that the DEC had been unresponsive - rhetorically asking in February, “How many emails can I send?” - FOIL (Freedom of Information Law) records showed the DEC had been formally contacting the town regarding these alleged violations as early as November 2025.

In his latest correspondence, Sherman reiterated that the DEC’s primary goal is environmental safety.

“The no-rise analysis must be performed if the material is to remain,” he wrote, adding that the Division of Materials Management may still have the final say on whether the “solid waste” can stay at the site at all.

For now, the town of Hancock has directed its Floodplain Administrator to transmit these requirements to Johnston & Rhodes. While Vernold maintains that the path forward is “orderly,” for residents like Elmore and Sam Rowe who have attended monthly town council meeting since the end of 2025 requesting answers, an action plan and offering solutions, the ten-month wait for transparency continues.

“The law doesn’t discriminate,” Rowe told council members in February. “You’ve got to treat them (Johnston & Rhodes) like you treat everybody else.”

DEC officials, following a request for comment after Vernold’s press release was received, responded: “The New York State Department of Environmental Conservation (DEC) is actively conducting a comprehensive investigation into community water quality and environmental complaints in East Branch, Delaware County, and is requiring corrective actions to address any violations of environmental laws and regulations observed.”

DEC remains committed to ensuring the protection of water quality and flood control infrastructure for all New Yorkers to safeguard human health and the environment and hold violators accountable.”

To view the DEC's April 10 letter, click here.